Overview

This Foundations Project included two remote submerged flight conveyors and related pipe rack foundations.

Project Challenges:

  • Start of major foundations was delayed; worked with the owner to develop a revised schedule that met all other site contractor’s needs.
  • Concrete supply in the area was limited; completed concrete pours in early morning hours to ensure suppliers could provide enough concrete.

Bowen Resourceful:

  • Used experience on similar projects to help owner develop revised schedule after initial delays by the site work contractor.

Bowen Responsive:

  • Bowen performed additional site work to support other contractors at the request of the owner.

Bowen Results:

  • On-time delivery and project completed with a great safety record.

Project Scope:

  • Site Work
  • Civil/ Concrete Work

Project Specs:

  • 5900 CY of Excavation Backfill
  • 6000 CY of Concrete
  • 650 Tons of Rebar
  • 53,500 SF of Formwork
  • 2854 Anchor Bolts

 

  • Project Location : Belmont, NC
  • Project Type : Foundations
  • Client : Duke Energy
  • Total Contracts : $7,500,000
  • Project's Link : Project 1-Pager